Sheet Index Checking out All Sheets

Why do I need to check out every sheet dgn in the sheet index when I am updating the sheet index? I currently have a plan set with 200 sheets and counting and the time it takes to update the index is frustrating. If i am only adding in additional sheets or reorganizing sheets, it takes a lot of time to wait for the sheet index to process. It also locks my team members out of files while I am completing the updates. Doesn't the 'sync' model function accomplish all the needed updating at the end? Is there a way to only push the updates when the sheet index is checked back in?

  • Guest
    Jun 23, 2025

    Moving to MicroStation ideas.